Fernhill — Memory Support Dining
Bolton Clarke · Fernhill, 88 Chatswood Rd, Daisy Hill QLD 4127
Memory support dining room. Round tables only, no corners, contrast between floor, table and chair.
Open on this project
- Ex-factory — all suppliers — Westbourne moved out 6 days; delivery DKT-2026-0344 has slipped.
Opened
1 Jun 2026
Handover target
25 Sep 2026
Days to go
56
Value ex GST
$30,850.78
Margin
$11,090.98 · 36.0%
Lines
6
Delivery plan
1 of 5 complete- Quote accepted 24 Jun 2026 TG Complete
- All POs confirmed Freight PO-2026-0229 still in draft. 10 Jul 2026 JW In progress
- Ex-factory — all suppliers Westbourne moved out 6 days; delivery DKT-2026-0344 has slipped. 2 Sep 2026 PR At risk
- Site delivery & placement 11 Sep 2026 PR Not started
- Practical completion & final claim 25 Sep 2026 JW Not started
QA checkpoints
0 pass · 0 defectNothing inspected yet. QA runs at delivery, area by area.
Site deliveries
Logistics →| DKT-2026-0344 | Memory support dining & sitting Ridgeway Furniture Freight · 2 consignments · 63 cartons | 11 Sep 2026 8:00am – 1:00pm | Slipped |
Documents
0Nothing filed against this project yet.
Billing
$10,180.76 invoiced of $33,935.86 · $23,755.10 to go
- Deposit INV-10659 $10,180.76
Factories on this job
- Westbourne Furniture Manufacturing PO-2026-0225 · $8,680.00 In production
- Riverina Timber Works PO-2026-0226 · $2,060.40 Confirmed
- Adelaide Hills Joinery PO-2026-0227 · $4,029.00 In production
- Kembla Upholstery Co. PO-2026-0228 · $2,850.40 Confirmed
- Ridgeway Furniture Freight PO-2026-0229 · $2,140.00 Draft
Site access
Dock, single goods lift 1500 x 1200.
Rebecca Ng · (07) 3363 2800
Responsibilities
- SalesTony Gooley
- CoordinationPriya Raman
- Client contactRebecca Ng
- Site contactRebecca Ng
- Payment terms45 days EOM